Research · World market

PCB laminate lead times in late 2026: why the board date depends on the CCL

A Taiwanese board maker showed E-glass laminate at 8 to 20 weeks across its three suppliers in November 2026. How laminate weeks reach a board's date, and the checks buyers make.

MPBxChange research · Published 14 November 2026 · 12 min read · 25 sources

PCB laminate lead times in late 2026: why the board date depends on the CCL
Illustration: MPBxChange

A printed circuit board cannot be built before its laminate arrives. In late 2026 that wait set the delivery date of many boards. At an investor conference on 12 November 2026, Allied Circuit (博智電子, TPEx 8155), a Taiwanese maker of boards for servers, industrial computers and IC testers, showed lead times of 8 to 20 weeks for E-glass copper clad laminate (CCL) across its three laminate suppliers, and 4 to 12 weeks for a higher grade it labels K-glass.[1][2][4] This note sets out what the company reported, how laminate weeks sit in front of fabrication in a quoted board date, where in the chain from glass yarn to laminate supply is reported tight, and the checks a buyer sourcing boards in Thailand can make, with evidence to 14 November 2026.

Key points

  • Allied Circuit's slides, filed on MOPS, list E-glass laminate at 16 to 20 weeks from supplier A, 12 to 16 weeks from supplier B and 8 to 12 weeks from supplier C, against 4 to 12 weeks for the K-glass grade. The slides leave the suppliers unnamed. Economic Daily News reported the same day that the three are Taiwan's three largest CCL makers and that entry-level grades had lengthened markedly.[2][5]
  • The figures describe one board maker's suppliers in November 2026. Other channels report different numbers: a PCB supplier quoted by VersaLogic put several material families at about 8 to 10 weeks in October and selected higher-performance materials at 24 to 32 weeks, as base lead times under allocation.[6]
  • When the laminate is neither in a plant's stock nor allocated to the build, its lead time comes before fabrication starts, so the earliest board date is the laminate wait plus the plant's fabrication time.
  • Glass cloth is the reported constraint. Thin styles 2116, 1080 and 1078 are the tightest and weaving looms limit how fast supply can grow; Ventec put the supply gap at about 30% in low-Dk cloth and 15% to 20% in thin cloth, with tightness possibly lasting beyond the second quarter of 2027.[8][15]
  • Nan Ya said price rises had spread from high-end to baseline specifications, and told Commercial Times that securing material and lead time had become the focus of purchasing.[12][8]
  • Two documents set how much room a buyer has: the approved stack-up, and whether it names a laminate by brand or by IPC-4101 specification sheet. A substitute that is not already approved goes through the laminate maker's evaluation and then the customer's.[20][21][23]

Allied Circuit's laminate lead times, 12 November 2026

Allied Circuit presented at an institutional investor conference hosted by KGI Securities in Taipei at 14:30 on 12 November 2026, according to its MOPS listing, which carries the slides in Chinese and English.[1][3] MOPS lists the company as 博智電子股份有限公司, with the English name Allied Circuit Co., Ltd. and stock code 8155.[4] The slides describe its server boards as 8 to 30 layers on laminate of the loss grades it labels M6 to M7, and its boards for industrial computers and IC testers as built on M4 to M6 grades.[2]

Slide 16, "Upstream Materials Status", gives the lead time of each supplier by glass grade, with the company's action plan for each:[2][3]

Laminate supplier (unnamed in the slides)E-glass laminateK-glass laminateAllied Circuit's stated position
Supplier A16 to 20 weeks8 to 12 weeksA second source from the supplier's China plant, and a larger quota allocation, in 2027
Supplier B12 to 16 weeks4 to 6 weeksStable delivery; sufficient quota allocation
Supplier C8 to 12 weeks6 to 8 weeksAllied Circuit is a key account; sufficient quota allocation

At every supplier the E-glass grade, the entry-level reinforcement, carries the longer wait. Economic Daily News reported the presentation that afternoon: among Taiwan's three largest CCL makers, lead times for entry-level grades such as E-glass cloth had lengthened markedly, to about 16 to 20 weeks, while higher grades such as K-glass cloth were relatively shorter.[5] The paper also reported the company's response: qualifying substitute materials from makers in mainland China, including the China plants of existing Taiwanese suppliers and new mainland makers, while seeking quota; updating customers on lead times regularly; and helping customers qualify substitutes to keep supply stable.[5] On the customer side, the slide lists longer-term commitments from customers and the qualification of second sources.[2]

MPBxChange reads the split between grades as the cloth shortage passing into laminate. Glass makers moved looms and furnaces to specialty cloth for AI hardware, and the queue has formed in the E-glass styles that mainstream laminate uses.[11][8] The two shortages are explained in PCB material shortage 2026.

Reported laminate lead times on one scale

Figures from other channels differ by grade, maker and date. On 4 November 2026 VersaLogic, a US maker of embedded computers, relayed a PCB supplier's account that October CCL lead times vary significantly by supplier and material: several material families at about 8 to 10 weeks, selected higher-performance materials at 24 to 32 weeks, and some specific materials at six months or more. The supplier notes that these are base lead times under allocation, and that requirements above allocation are reviewed case by case.[6] In March 2026 ILFA, a German board maker, reported FR-4 laminate from major suppliers at about four weeks, up from a few days, and advanced high-Tg and low-Dk laminates at up to 140 days, which is 20 weeks.[7]

Allied Circuit's three laminate suppliers, as shown in its slides of 12 November 2026[2]

  • Supplier A, E-glass laminate
  • Supplier A, K-glass laminate
  • Supplier B, E-glass laminate
  • Supplier B, K-glass laminate
  • Supplier C, E-glass laminate
  • Supplier C, K-glass laminate

A PCB supplier quoted by VersaLogic, October 2026 lead times[6]

  • Several material families
  • Selected higher-performance materials, under allocation

ILFA, a German board maker, March 2026[7]

  • FR-4 laminate from major suppliers, about
  • Advanced high-Tg and low-Dk laminates, up to (140 days)
Weeks from the day the laminate is requested
  • E-glass laminate, the entry-level grade in Allied Circuit's slides
  • Other grades and sources; the lighter end of a bar is the spread the source gives
  • Fabrication starts here, when the laminate arrives; its length depends on the plant's quote and is not drawn
Laminate weeks come before fabrication: reported lead times, to one scale. When a board's laminate is neither in the plant's stock nor allocated to the build, fabrication cannot start until it arrives, so the earliest board date is the laminate lead time plus the plant's fabrication time. Each figure is one source's report for its own suppliers, grades and date; the rows are drawn together to compare magnitude. Sources: Allied Circuit (MOPS), VersaLogic, Evertiq.

The sources show no single market lead time. Allied Circuit's suppliers quote E-glass longer than the higher grade, while VersaLogic's supplier quotes higher-performance materials longer. Both describe the same mechanism: the wait for laminate depends on the supplier, the grade and the allocation that the supplier gives a particular customer.

How laminate weeks reach the board date

A fabricator starts a multilayer board when the cores (CCL) and bonding sheets (prepreg) of its stack-up are on hand. Three cases follow from where that material stands.

  1. In the plant's stock, or already delivered: the board date is the fabrication time the plant quotes.
  2. Allocated to the build by the laminate maker, with a delivery date: fabrication starts on that date, and the board date follows it.
  3. Still to be bought: the laminate lead time comes first. At supplier A's E-glass lead time of 16 to 20 weeks, fabrication cannot start until 16 to 20 weeks after the laminate is requested.[2]

Two quotes for the same board can therefore carry different dates because of the laminate's position, before any difference in fabrication capacity. A plant that holds allocation, or makes its own laminate, can quote from the first two cases. KCE Electronics, a board maker listed in Thailand, said on 5 November 2026 that a shift in supply allocation toward AI server applications had further restricted the materials available for conventional PCB production, and that the internal supply of its laminate subsidiary, Thai Laminate Manufacturer, helped moderate the impact of rising laminate and prepreg costs during the third quarter.[19]

Statements on laminate and glass cloth, October to November 2026

Laminate makers, glass makers and board makers described the same constraint through October and November. The table lists the dated statements; the sections below take up the chain and the buyer's checks.

DateCompany or sourceReportedSource
14 October 2026Kingboard Laminates, reported by YicaiLaminate and prepreg made with glass cloth of style 2116 or thinner up 15%, citing strong demand for thin cloth and tight supply of glass cloth and yarn[10]
20 October 2026Unimicron's chairman, reported by Economic Daily NewsBottlenecks in T-glass cloth, CCL and ABF; some specific machines at lead times of up to 30 months; a gap of about 20% possible in the most critical materials in 2027[18]
22 October 2026Supply-chain sources and Nan Ya, reported by Commercial TimesThin cloth 2116, 1080 and 1078 tightest; looms the main bottleneck; securing material and lead time the focus of purchasing[8]
22 October 2026Supply-chain sources, reported by TechNewsGlass cloth and CCL increases of about 10% to 15% from as early as November; buyers shifting from price and product choice to securing material and lead time[9]
27 October 2026Nan Ya Plastics, investor presentationPrice rises spread from high-end to baseline specifications; equipment suppliers also short[12]
29 October 2026Elite Material (EMC), investor presentationLaminate capacity of 5.85 million sheets a month in 2026, planned at 15.25 million in 2030[17]
6 November 2026China Jushi and Sinoma, reported by Sina FinanceElectronic cloth supply still tight; 2027 supply growth hard to match demand; electronic yarn expected to stay short throughout 2027[14]
12 November 2026Nan Ya, reported by Economic Daily NewsShort-term measures: CCL process improvements, more specialty yarn spinning positions in Taiwan and China, more weaving looms, contributing from the fourth quarter of 2026 into 2027[13]
12 November 2026Allied CircuitE-glass laminate at 8 to 20 weeks across three suppliers[2][5]
13 November 2026Ventec, reported by Commercial TimesSupply gap of about 30% in low-Dk cloth and 15% to 20% in thin cloth; tightness possibly beyond the second quarter of 2027; its raw material supply rate up from about 60% to 80% this year[15]

Ventec also expected material prices to have room to rise in the first quarter of 2027.[15] TechNews reported that buyers' purchasing strategy had moved from price and product choice toward securing supply and lead time, and supply-chain sources expected the shortage of glass cloth to ease between the second half of 2027 and 2028, depending on equipment deliveries, new capacity and product changes.[9][8]

Where the chain is tight: yarn, cloth, laminate

A laminate is glass yarn woven into cloth, impregnated with resin and pressed with copper foil. Each stage feeds the next, so a constraint upstream reaches the board date through the laminate wait.

  1. 1Glass yarn

    Melted in furnaces and drawn into filament

    • 2027Electronic yarn expected to stay short throughout 2027 (Sinoma); 2027 cloth supply growth hard to match demand (China Jushi)[14]
  2. 2Glass cloth

    Woven on looms into styles such as 7628, 2116, 1080 and 1078

    Main reported bottleneck: weaving looms

    • 3,333 / 5,833Kingboard's looms in operation, 2025 and planned by 2028; high-performance looms virtually impossible to source[11]
    • 2,400 / 3,600World output of the relevant looms a year, about, and possibly in 2027 (supply-chain sources)[8]
    • 30%Supply gap in low-Dk glass cloth, about (Ventec)[15]
    • 15-20%Supply gap in thin electronic-grade cloth (Ventec)[15]
    • ThailandQ3 2027Fulltech glass cloth, Chachoengsao: mass production planned[25]
  3. 3Prepreg and laminate (CCL)

    Cloth impregnated with resin; pressed with copper foil into cores

    • 8-20Weeks for E-glass laminate across Allied Circuit's three suppliers[2]
    • 5.85 / 15.25EMC laminate capacity, million sheets a month, 2026 and planned for 2030[17]
    • 30Months: lead time of some specific machines, up to (Unimicron)[18]
    • Thailand189.2 / 180.2TUC, Chon Buri, and Doosan, Samut Prakan: laminate and prepreg plants approved by the BOI, US$ million[24]
    • Thailand0.1Ventec, Thai plant established 2025: million laminate sheets a month[16]
  4. 4Board plant

    Starts a board when the stack-up's laminate and prepreg are on hand

    Allocation toward AI servers restricted materials for conventional boards (KCE); quota and second sources (Allied Circuit)[19][2]

  5. 5Buyer

    Receives the board date that the laminate position allows

    Securing material and lead time became the purchasing focus (Nan Ya)[8]

The laminate chain, from glass yarn to the buyer, and where supply is reported tight. Each stage feeds the next, so a shortage of thin glass cloth reaches the board date through the laminate wait. Figures are as reported by the named companies or press, October to November 2026, with Kingboard's loom figures from its 2026 interim results; capacities and dates for Thai plants are plans. Pairs of figures read earlier, then later. Sources: Kingboard Laminates, Commercial Times, Sina Finance, Allied Circuit, Elite Material, Economic Daily News, KCE Electronics, Ventec, BOI, Anue.

The yarn stage is short of the traditional grades. Kingboard Laminates reported in August that existing capacity had largely shifted to AI-related products, causing severe shortages of traditional electronic glass yarn and fabric.[11] In November China Jushi said electronic cloth supply was still tight and that 2027 supply growth would struggle to match demand, and Sinoma expected electronic yarn to stay short throughout 2027.[14]

The cloth stage is where the sources place the bottleneck. Supply-chain sources cited by Commercial Times put world output of the relevant weaving looms at about 2,400 a year, possibly 3,600 in 2027, with actual deliveries still to be seen.[8] Kingboard reported that high-performance weaving looms had become virtually impossible to source, and planned to raise its looms in operation from 3,333 in 2025 to 5,833 by 2028.[11] Nan Ya is adding specialty yarn spinning positions and weaving looms as short-term measures that contribute from the fourth quarter of 2026 into 2027.[13]

At the laminate stage, capacity is being added on multi-year plans. EMC's October presentation shows laminate capacity of 5.85 million sheets a month in 2026 and a plan of 15.25 million in 2030, including a plant in Penang, Malaysia.[17] Equipment paces such plans: Unimicron's chairman said on 20 October that some specific machines had lead times of up to 30 months.[18]

Thailand's own laminate and cloth supply arrives in steps. Ventec's November presentation lists a Thai plant established in 2025 with capacity of 0.1 million sheets a month.[16] The BOI has approved laminate and prepreg plants of Taiwan Union Technology in Chon Buri, at US$189.2 million, and of Doosan Electro-Materials in Samut Prakan, at US$180.2 million.[24] Fulltech plans mass production of glass cloth in Chachoengsao in the third quarter of 2027.[25] Dates and capacities for every Thai materials plant are set out in glass cloth and laminate for Thai PCB plants and PCB materials made in Thailand.

Allocation, substitutes and requalification

Whether laminate weeks are added to a board date depends on three things a buyer can check: how the stack-up names the laminate, where the laminate stands, and whether a substitute is already approved.

  1. 1How does the approved stack-up name the laminate?[20][21]

    • By brand and product: one supply channel
    • By IPC-4101 specification sheet: any material certified to that sheet's requirements can be offered, within the drawing's other limits
  2. 2Where is the laminate and prepreg for this build?[2][6][19]

    • In the plant's stock: the board date is fabrication time
    • Allocated by the laminate maker, with a delivery date: fabrication starts on that date
    • Still to be bought: the laminate lead time comes first
  3. 3If the named laminate is short, is a substitute already approved by the board's customer?[5][21][23]

    • Yes: build on the approved alternate
    • No: requalify, first by the laminate maker's own evaluation, then by the customer's evaluation of laminate made with the new material
  4. Board date = laminate wait, if any + the plant's fabrication time

  • No laminate weeks added
  • Weeks set by the allocation date
  • Laminate lead time or qualification time added
Three checks that decide whether laminate weeks come before fabrication. The checks follow IPC-4101's classification by specification sheet, NCAB's guidance on specifying laminate, the allocation statements of Allied Circuit, VersaLogic's supplier and KCE Electronics, and the two-stage evaluation of a substitute material reported by Dealsite. Qualification time is set by each customer's plan.

IPC-4101 classifies laminate and prepreg by specification sheet. Each specification sheet outlines requirements for both laminate and prepreg for each product grade, and is organised by reinforcement, resin system or construction; the line items on a sheet are the requirements a material must meet to be certified to it. When a material is certified to more than one sheet, the strongest performance requirements apply, and when no revision of IPC-4101 is called out, the latest revision applies.[21] The current revision, IPC-4101F, is dated 1 February 2026.[22]

NCAB Group, a PCB supplier, wrote in May 2026 that specifying laminate by brand name locks a design into a single supply channel, while specifying materials to IPC-4101 with defined slash sheets allows significantly more flexibility, and that allowing more than one acceptable slash sheet where performance permits enables regional sourcing.[20]

Qualifying a substitute takes two evaluations. Dealsite reported in September 2026 that Doosan Electro-Materials evaluates glass cloth from Chinese makers itself and, once it judges the quality sufficient, sends CCL made with it to customers such as Samsung Electro-Mechanics for further evaluation.[23] Allied Circuit said it helps its customers qualify substitute materials.[5] Ventec said that certification of its M7 to M9 low-loss materials for new AI data centres in the United States and China was being accelerated, with results expected from after the first quarter of 2027.[15] The length of each qualification is set by the customer's own plan.

Checks for buyers sourcing boards in Thailand

Boards built in Thailand draw on the same laminate makers and the same allocation as boards built elsewhere; the Thai plants above shorten the route for part of the laminate and prepreg from 2026 to 2028. The checks below follow the standard and the company statements cited in this note.

  1. Read the approved stack-up: does it name the laminate by brand and product, or by IPC-4101 specification sheet number?[20][21]
  2. Ask the plant whether the laminate and prepreg for the stack-up are in stock, allocated with a delivery date, or still to be bought; the board date follows from the answer.[2][6]
  3. Ask which glass styles the stack-up uses. Styles 2116, 1080 and 1078 were reported as the tightest in October.[8][10]
  4. Ask which alternate materials the board's customer has already approved, and to which specification sheet each is certified.[21][5]
  5. Where no alternate is approved, plan the laminate maker's evaluation and the customer's evaluation into the schedule before switching material.[23]
  6. Ask whether the plant makes its own laminate or holds quota with laminate makers in Thailand or the region.[19][2]

The questions to ask a PCB factory set out the documents that support these answers, and the Thailand PCB tracker lists the plants in the country.

Data and method

This note draws on the investor-conference listing and slides that Allied Circuit filed on MOPS for 12 November 2026, its MOPS company profile and the Economic Daily News report of the same day; investor presentations of Nan Ya Plastics, Elite Material and Ventec filed on MOPS; KCE Electronics' management discussion and analysis for the third quarter of 2026; Kingboard Laminates' 2026 interim results; a Board of Investment release; IPC-4101E-WAM1 and the IPC-4101F catalogue entry; publications of NCAB Group and VersaLogic; and reports by Commercial Times, Economic Daily News, TechNews, Yicai, Sina Finance, Anue, Dealsite and Evertiq. All were read on 14 November 2026.

The lead times in Allied Circuit's slides are that company's reported experience with three laminate suppliers, which the slides leave unnamed; this note keeps them unnamed and applies the figures to that company's supply. Statements by laminate makers are taken from their own filings or as reported by the named press, and supply-chain statements are as the press reports them. Lead times vary by grade, glass style, supplier, customer and date; the diagram draws the reported figures on one scale to compare their size. Capacities and dates of new plants are the companies' plans. Interpretation is MPBxChange analysis.

Sources

  1. official Taiwan Stock Exchange, Market Observation Post System (MOPS) (2026). 法人說明會一覽表: 8155 博智, 115/11/12 14:30 (investor conference listing, 12 November 2026). MOPS (公開資訊觀測站). back to text
  2. company Allied Circuit Co., Ltd. (2026). 2026 Institutional Investor Conference, November 2026 (slides filed on MOPS, English; slide 16, Upstream Materials Status). MOPS (公開資訊觀測站). back to text
  3. company 博智電子股份有限公司 (Allied Circuit Co., Ltd.) (2026). 2026 年博智電子法說會 (slides filed on MOPS, Chinese; slide 16, 上游材料的現況). MOPS (公開資訊觀測站). back to text
  4. official Taiwan Stock Exchange, Market Observation Post System (MOPS) (2026). 公司基本資料: 8155 博智 (company profile). MOPS (公開資訊觀測站). back to text
  5. press Economic Daily News (經濟日報) (2026). 博智法說會/將伺服器打入太空新專案未來具參與機會. United Daily News (udn.com). back to text
  6. company VersaLogic Corporation (2026). Supply Chain Brief: Market Conditions in 2026 (update of 4 November 2026). VersaLogic. back to text
  7. press Evertiq (2026). PCB lead times extend as material shortages and AI demand strain supply chains. Evertiq. back to text
  8. press Commercial Times (工商時報) (2026). 薄玻纖布、CCL又缺貨 下月看漲15% 南亞直言市場已「沒得挑」. Commercial Times (ctee.com.tw). back to text
  9. press TechNews (科技新報) (2026). 玻纖布、CCL 缺貨壓力升溫,11 月醞釀漲價. TechNews. back to text
  10. press Yicai (第一财经) (2026). 覆铜板巨头建滔积层板下发年内第八次涨价通知. Yicai. back to text
  11. company Kingboard Laminates Holdings Limited (2026). Interim Results Announcement, six months ended 30 June 2026. HKEXnews (Hong Kong Exchanges and Clearing). back to text
  12. company Nan Ya Plastics Corporation (2026). 3Q26 investor conference presentation, 27 October 2026 (filed on MOPS). MOPS (公開資訊觀測站). back to text
  13. press Economic Daily News (經濟日報) (2026). 電子材料供需偏緊 漲價趨勢不變. United Daily News (udn.com). back to text
  14. press Sina Finance (新浪财经) (2026). 电子布价格近期再度走高 供需偏紧情况或将延续. Sina (新浪). back to text
  15. press Commercial Times (工商時報) (2026). 騰輝:CCL原料明年Q1續看漲. Commercial Times (ctee.com.tw). back to text
  16. company Ventec International Group (騰輝電子-KY) (2026). Investor conference presentation, 13 November 2026 (filed on MOPS; slide 8, Manufacturing Overview). MOPS (公開資訊觀測站). back to text
  17. company Elite Material Co., Ltd. (EMC, 台光電) (2026). Presentation, October 2026 (filed on MOPS for the conferences of 29 October 2026; page 13, EMC Advantages (2)). MOPS (公開資訊觀測站). back to text
  18. press Economic Daily News (經濟日報) (2026). 欣興董座:AI 帶動硬體黃金時期 2027年 PCB 載板材料缺口20%. money.udn.com. back to text
  19. company KCE Electronics Public Company Limited (2026). Management Discussion and Analysis, Quarter 3 ending 30 September 2026 (letter to the Stock Exchange of Thailand, 5 November 2026). KCE Electronics investor relations (kce.listedcompany.com). back to text
  20. company NCAB Group (2026). PCB design for supply stability. NCAB Group. back to text
  21. official IPC (2020). IPC-4101E-WAM1, Specification for Base Materials for Rigid and Multilayer Printed Boards (table of contents and section 1). IPC. back to text
  22. official IPC (2026). IPC 4101F:2026-02-01, Specification for Base Materials for Rigid and Multilayer Printed Boards (catalogue entry). DIN Media. back to text
  23. press Dealsite (딜사이트) (2026). "CCL 확보 해달라" 삼성전기, 두산에 SOS…中 대체재 개발 '재촉'. Dealsite. back to text
  24. official Thailand Board of Investment (BOI) (2026). Thailand Approves $1.99 Billion in New Investment, Led by AI and Advanced Electronics. BOI One Start One Stop Investment Center (OSOS). back to text
  25. press Anue (鉅亨網) (2026). 富喬泰國新廠動土 擴展東南亞AI與低軌衛星關鍵材料布局. Anue (cnyes.com). back to text

How to cite: MPBx Research Team (2026). PCB laminate lead times in late 2026: why the board date depends on the CCL. MPBxChange research. https://www.mpbxchange.com/research/pcb-laminate-lead-times-ccl-2026